Domain walkways upgrade
Introduction
| What will be involved
| Programme of works
| Closures during the upgrade
Introduction
We're getting on with upgrading a majority of the walking tracks that run throughout the Auckland Domain from January through to June 2008.
The improvements will result in a network of tracks that are accessible and more enjoyable in all weather conditions.
What will be involved
Auckland City Council contractors will be upgrading one to two tracks at a time. Improvement work includes the resurfacing and upgrading of
steps and surface drainage. Some tracks may require more work than others.
Programme of works
| Track |
Planned upgrade date |
| Lower Domain Drive to Carpark Track |
Late January to early February |
| Glade Path |
Late January to late February |
| Nikau Walk |
Late February to early March |
| Lovers Walk/Glade Walk link |
First week of March |
| Lovers Walk |
Early March to early April |
| Lovers Walk/Centennial Walk link (lower and upper) |
Early to mid April |
| Domain Walk Part 1 |
Mid-April to mid-May |
| Bush Walk |
Mid-May |
| Bledisloe Walk |
Mid-May to mid-June |
| Domain Walk Part 2 |
Early to late June |
You can view the site plan showing the locations of the walkways in PDF format:
Domain walkways upgrade siteplan (420kb PDF)
To view PDFs download Acrobat Reader from the
Adobe website. Further help on how to view PDFs.
Closures during the upgrade
In some cases the tracks be closed while works are in progress. Contractors will be required to close some of the tracks while work is taking place.
Other tracks will remain open but caution should be taken.
Signs will indicate whether or not a track is closed during its upgrade or if caution is necessary.
To ensure you encounter minimal disruption while improvements are taking place, keep in mind the schedule above and try to plan alternate routes
just in case.
Published January 2008